City of Alliance installing underground conduit

Posted Jul 31, 2020 5:17 PM

Alliance – The City of Alliance has contracted CenCon, a soil boring company from Gering, NE., to install underground conduits in a portion of the Park Knoll Addition. These conduits will be used to install new electrical lines.

Work on this project is scheduled to begin on Monday, August 3, 2020.

The majority of the work will be along both sides of Niobrara from 20th Street to Park Knoll. A portion of the work will also be performed along the North Side of Park Knoll from Box Butte to Sweetwater.

This project is expected to last two to three weeks. If you have questions or concerns, please call the Electric Department at (308) 762-1907 or the Utility Office at (308) 762-5075.