Work set to begin on U.S. 30 from Ogallala to Roscoe

Posted Mar 03, 2023 11:49 AM

NDOT

NORTH PLATTE — Weather permitting, work will begin March 6, on US. 30, from reference post 127.54 to reference post 133.69, according to the Nebraska Department of Transportation. Paulsen Inc. of Cozad is the contractor for this project. Work includes grading, milling, concrete overlay, asphalt surfacing, and seeding. Traffic will be maintained with lane closures for the duration of the project. A 12-foot width restriction will be in effect.

A future detour of U.S. 30 is anticipated to begin March 12 and end mid-June for the concrete overlay work. Further detour information will be provided prior to the detour. Anticipated project completion is July 2023.